A BIM-Informed Multi-Objective Work-Zone Scheduling Model for Improving Crew Continuity and Resource Stability in Multi-Story Building Projects

Author(s): Sultan Alkarawi 1 , Firas Kh. Jaber 2 , Aws S. Noaman 3
Author(s) information:
1 Civil Engineering Department, Collage of Engineering, University of Diyala, Baqubah, Iraq
2 Engineering Technical Collage Baghdad, Middle Technical University, Baghdad, Iraq
3 Environmental Engineering Department, College of engineering, Tikrit University, Tikrit, Iraq

Corresponding author

Construction scheduling methods often lack effective integration of daily resource stability, work-zone sequencing, and specialist crew continuity, particularly in multi-story projects employing bottom-up floor sequencing. This study developed a BIM-informed multi-objective work-zone scheduling model to address these challenges. The model was applied to a five-story office building comprising 15 work zones and six repetitive activities, represented by 90 activity-zone records. The Non-dominated Sorting Genetic Algorithm II (NSGA-II) was employed to minimize work-package duration, cumulative crew idle time, and daily resource variation while satisfying precedence, crew exclusivity, non-preemption, workforce, workspace, concurrency, and bottom-up progression constraints. Ten independent runs were performed with a population size of 100 over 200 generations. The selected solution (168, 380, 219) achieved a work-package duration of 168 working days, cumulative crew idle time of 380 days, and a resource variation value of 219, representing reductions of 58.4%, 78.9%, and 18.6%, respectively, compared with sequential execution. An exhaustive evaluation of all 7,776 feasible sequences reproduced the same two-vector Pareto front, confirming the complete set of non-dominated solutions within the modeled search space. Sensitivity analysis identified crew efficiency and allowable zone concurrency as the primary factors influencing scheduling performance. The proposed model offers a practical decision-support tool for construction planners to balance project duration, crew continuity, and resource stability while maintaining a feasible and operationally interpretable bottom-up construction sequence.

Tomczak, M.; Jaśkowski, P. (2020). Crashing construction project schedules by relocating resources. IEEE Access, 8, 224522‒224531. https://doi.org/10.1109/ACCESS.2020.3044645.

Yao, Z.; Zhang, L.; Luo, J.; Wei, S. (2025). Resource leveling strategy integrating soft logic and crew interruption in repetitive projects. Computer-Aided Civil and Infrastructure Engineering, 40, 3118‒3146. https://doi.org/10.1111/mice.13483.

Amarkhil, Q.; Elwakil, E. (2024). Enhanced planning and scheduling in building construction projects: An innovative approach to overcome scheduling challenges. International Journal of Construction Management, 24, 1719‒1729. https://doi.org/10.1080/15623599.2023.2286888.

Vahidi, J.; Golmaei, S. (2025). Optimizing construction scheduling using the sine cosine algorithm (SCA) with building information modeling (BIM). Results in Engineering, 107100. https://doi.org/10.1016/j.rineng.2025.107100.

Jaiswal, S.; Kar, S. (2025). A decision support system for optimizing labor acquisition in construction. Journal of Construction Engineering and Management, 151, 04025211. https://doi.org/10.1061/JCEMD4.COENG-16841.

Olaya, S.; Tibaná, C.; Sánchez, O.; Castañeda, K.; Torres, K. (2026). Human resource planning for building construction processes through the integration of BIM and line of balance. Buildings, 16, 1919. https://doi.org/10.3390/buildings16101919.

Wang, L.; Li, J.; Ye, Q.; Li, Y.; Feng, A. (2024). Automatic planning method of construction schedule under multi-dimensional spatial resource constraints. Buildings, 14, 3231. https://doi.org/10.3390/buildings14103231.

Wefki, H.; Elnahla, M.; Elbeltagi, E. (2024). BIM-based schedule generation and optimization using genetic algorithms. Automation in Construction, 164, 105476. https://doi.org/10.1016/j.autcon.2024.105476.

Shen, Z.; Wu, J. (2025). Multiobjective ant colony system algorithm for component-level construction schedule optimization. Journal of Construction Engineering and Management, 151, 04025002. https://doi.org/10.1061/JCEMD4.COENG-15827.

Altuwaim, A.; El-Rayes, K. (2021). Multiobjective optimization model for planning repetitive construction projects. Journal of Construction Engineering and Management, 147, 04021072. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002072.

Dai, G.; Liao, M.; Zhang, R. (2023). Resource levelling in repetitive construction projects with interruptions: An integrated approach. Journal of Civil Engineering and Management, 29, 93‒106. https://doi.org/10.3846/jcem.2023.17568.

Abdelbasset, E.; Hassan, A.; Amer, N.H.; Khalifa, Y.A. (2023). Optimizing the number of crews working in parallel and their work sequence to minimize project duration and cost for repetitive construction projects. Innovative Infrastructure Solutions, 8, 288. https://doi.org/10.1007/s41062-023-01233-3.

Saad, D.A.; Masoud, M.; Osman, H. (2021). Multi-objective optimization of lean-based repetitive scheduling using batch and pull production. Automation in Construction, 127, 103696. https://doi.org/10.1016/j.autcon.2021.103696.

Lazari, V.; Chassiakos, A.; Karatzas, S. (2024). Multi-objective resource-constrained scheduling in large and repetitive construction projects. Algorithms, 17, 351. https://doi.org/10.3390/a17080351.

Tomczak, M.; Jaśkowski, P. (2020). New approach to improve general contractor crew’s work continuity in repetitive construction projects. Journal of Construction Engineering and Management, 146, 04020043. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001824.

Chen, Y.; Ye, L.; Li, R.; Zhao, X. (2023). A multi-period constrained multi-objective evolutionary algorithm with orthogonal learning for solving the complex carbon neutral stock portfolio optimization model. Journal of Systems Science and Complexity, 36, 686‒715. https://doi.org/10.1007/s11424-023-2406-3.

Deb, K.; Pratap, A.; Agarwal, S.; Meyarivan, T. (2002). A fast and elitist multiobjective genetic algorithm: NSGA-II. IEEE Transactions on Evolutionary Computation, 6, 182‒197. https://doi.org/10.1109/4235.996017.

Jaśkowski, P.; Biruk, S. (2020). Scheduling of repetitive construction processes with concurrent work of similarly specialized crews. Journal of Civil Engineering and Management, 26, 579‒589. https://doi.org/10.3846/jcem.2020.12914.

Blank, J.; Deb, K. (2020). Pymoo: Multi-objective optimization in Python. IEEE Access, 8, 89497‒89509. https://doi.org/10.1109/ACCESS.2020.2990567.

Long, L.D. (2024). A non-unit repetitive construction project scheduling with uncertainties. Automation in Construction, 164, 105428. https://doi.org/10.1016/j.autcon.2024.105428.

Su, R.; Aviles, J.S. (2025). Construction scheduling optimization of prefabricated buildings under resource constraints based on an improved whale optimization algorithm. International Journal of Computational Intelligence Systems, 18, 166. https://doi.org/10.1007/s44196-025-00898-1.

About this article

SUBMITTED: 04 September 2026
ACCEPTED: 06 October 2026
PUBLISHED: 10 October 2026
SUBMITTED to ACCEPTED: 33 days
DOI: https://doi.org/10.53623/csue.v6i2.1395

Cite this article
Alkarawi, S., Kh. Jaber, F. ., & S. Noaman, A. . (2026). A BIM-Informed Multi-Objective Work-Zone Scheduling Model for Improving Crew Continuity and Resource Stability in Multi-Story Building Projects. Civil and Sustainable Urban Engineering, 6(2), 309−322. https://doi.org/10.53623/csue.v6i2.1395